Deadline-driven work

The problem

Some work has a time by which it must be done: a report promised by 09:00, a fraud check that must finish before a payment settles, a transcoding job due before a broadcast. A priority alone does not capture this: a "normal" job due in five minutes is more urgent than a "high" job due tomorrow, but only once its deadline gets close.

The setup

Give tasks a deadline and, when known, a duration hint:

use std::time::{Duration, SystemTime};
use cronoq::{Priority, Task};

// Must be done in 10 minutes; usually takes ~2 minutes.
sched.submit(Task::new(report)
    .priority(Priority::Normal)
    .deadline_in(Duration::from_secs(600))
    .duration_hint(Duration::from_secs(120))).await?;

// Absolute deadline.
sched.submit(Task::new(batch)
    .deadline_at(SystemTime::now() + Duration::from_secs(3600))).await?;
await sched.submit(report, deadline_in=600, duration_hint=120)

Without a duration hint, cronoq uses the median runtime it has observed for the task's kind in that pool, then the pool's statistics, then the pool's default_duration (1 s).

How urgency works

From the deadline D and the estimated duration d, cronoq computes the latest start time LST = D − d. As the remaining slack LST − now shrinks below a horizon H = max(d, 5 s), the task's score gains urgency, rising linearly to 5000 at the latest start time. After that it keeps rising (100 points per second, up to +3000) so that an overdue task always ranks above one that is merely close. Within a priority class, tasks with deadlines are ordered by latest start time (earliest-deadline-first), which is optimal for meeting deadlines on a single resource.

Because 5000 exceeds the gap between high (1000) and low (10), a low task near its deadline overtakes fresh high work, but not critical work (10000).

What you get

  • Fewer missed deadlines with the same capacity. Work is reordered as deadlines approach, instead of strictly by priority or arrival.
  • Correct ordering among deadline tasks: earliest latest-start-time first.
  • Escalation for overdue work that is monotonic, so overdue tasks never fall behind ones that are merely close to their deadline.
  • Learned estimates. Duration estimates improve as tasks of the same kind complete.
  • Visibility. TaskContext::deadline (Rust) gives executors the deadline so they can choose a cheaper code path when time is short.
  • If the work must start at a specific time rather than finish by one, use a fixed start instead.
  • To add capacity when deadlines are at risk, combine deadlines with per-class wait SLOs on the pool's autoscaling configuration.